PETALING JAYA (Feb 23): A 4.4km four-lane road from Matang to Stapok in Kuching is on track for completion next month and should be open to motorists in April, reported Bernama.
The road is about 96% completed already, including a bridge linking both locations, said Works Minister Datuk Seri Fadillah Yusof (pictured).
Meanwhile, upgrading works for Jalan Batu 10 were expected to be completed in May and opened to the public in June.
SHARE
TOP PICKS BY EDGEPROP
RENT
FEATURED
Telok Panglima Garang Industrial Zone
Telok Panglima Garang, Selangor
RM 105,000
- beds |
- bath |
63000 sqft
SALE
FEATURED
Bandar Botanic Kelang
Bandar Botanic/ Bandar Bukit Tinggi, Selangor
RM 798,000
4 beds |
3 bath |
2400 sqft
SALE
FEATURED
Cheria Residences, Tropicana Aman
Telok Panglima Garang, Selangor
RM 1,980,000
4 beds |
5 bath |
3730 sqft
SALE
FEATURED
Telok Panglima Garang Industrial Zone
Telok Panglima Garang, Selangor
RM 2,500,000
- beds |
- bath |
63000 sqft
SALE
FEATURED
Elemen Residences @ Tropicana Aman
Telok Panglima Garang, Selangor
RM 1,400,000
4 beds |
5 bath |
2652 sqft