WCE project delay due to main contractor's poor performance — exco

IPOH (Aug 26): Construction of the West Coast Expressway (WCE), which starts from the Beruas junction to Taiping Selatan, is experiencing a delay compared to the actual schedule following the poor performance of the main contractor.

Perak Infrastructure, Energy, Water and Public Transport Committee chairman Datuk Mohd Zolkafly Harun said West Coast Expressway Sdn Bhd had taken over the remaining construction work in Section 11 of the Trong state constituency.

“The state government has also been briefed on the matter and the Malaysian Highway Authority (LLM) has committed to completing the remaining work on this project, which is another 48%, according to the new timeline.

“The project is expected to be completed in January 2024,” he said in reply to a question from Jamilah Zakaria (Barisan Nasional-Trong) at the 14th State Legislative Assembly sitting here today.

Mohd Zolkafly said the works being carried out are earthworks, rock blasting and the construction of structures and bridges, drains, slopes and others.

"Although construction work is allowed to continue, there are major constraints on the supply of building materials following the implementation of the movement control order (MCO) and enhanced MCO (EMCO),” he added.

Get the latest news @ www.EdgeProp.my

Subscribe to our Telegram channel for the latest stories and updates 

Click here for more property stories

Looking for properties to buy or rent? With >150,000 exclusive listings, including undervalued properties, from vetted Pro Agents, you can now easily find the right property on Malaysia's leading property portal EdgeProp! You can also get free past transacted data and use our proprietary Edge Reference Price tool, to make an informed purchase.
SHARE
RELATED POSTS
  1. Aneka Jaringan bags RM78m subcontract for West Coast Expressway project
  2. TCS wins RM177m contract for final section of West Coast Expressway
  3. 重点报道:高速公路对房价影响多大?