ECRL is nearly 21% complete, says Mohd Zuki

Bernama
5 June, 2021Updated:almost 5 years ago

JELI (March 7): The East Coast Rail Link (ECRL) project which is expected to be completed in 2026 has reached a progress rate of nearly 21% so far, said Malaysia Rail Link Sdn Bhd (MRL) chairman Tan Sri Mohd Zuki Ali.

Mohd Zuki said although the percentage indicated that the project is ahead of schedule, it is still a long way to go. He added that there are several issues such as land acquisition and site clearance that need to be solved.

“The most critical issue includes the approval from state governments on section A (Kota Bharu to Dungun), B (Dungun to Temerloh) and C (Temerloh to Port Klang), where we are still awaiting the approval from the Selangor state government.

"If we get the approval then the entire ECRL project will be able to be implemented (immediately) and to ensure that it does not fall behind schedule," he told reporters after visiting the Armed Forces Family Housing (RKAT) project site here today.

Also present was Minister in the Prime Minister’s Department (Economy) Datuk Seri Mustapa Mohamed.

On the participation of local contractors in the ECRL project, Mohd Zuki, who is also the Chief Secretary to the Government said it had so far reached 12% of the 40% target set by MRL, adding that more local contractors are expected to participate when the project’s civil works fully opened.  

Get the latest news @ www.EdgeProp.my

Subscribe to our Telegram channel for the latest stories and updates 

Click here for more property stories

Latest publications

Follow Us

Follow our channels to receive property news updates 24/7 round the clock.

whatsapp
telegram
facebook
CLOSEclear

Malaysia's Most
Loved Property App

The only property app you need. More than 200,000 sale/rent listings and daily property news.

App StoreGoogle Play
Mobile logo