Pan Borneo Highway: Works Ministry hopes no more delays, says Arthur

BERNAMA
22 July, 2022
Updated:over 3 years ago

TELUPID (April 22): The Works Ministry (KKR) hopes there will be no more delays in completing the Pan Borneo Highway, with the country having entered the Covid-19 transition to endemic phase, said Deputy Minister Datuk Arthur Joseph Kurup.

He acknowledged that the implementation of the Movement Control Order (MCO) to curb the spread of the Covid-19 pandemic was one of the main reasons that caused the delay in the highway's construction, thus resulting in delays to the maintenance of several roads in the Pan Borneo alignment.

"When the government implemented the MCO, there were many problems such as the shortage of workers and materials, closure of factories, and others. However, since there is no MCO now, we can now implement the work.

"KKR always monitors and receives implementation progress reports monthly to ensure contractors will complete the work according to the scope and schedule that had been agreed," he told reporters after visiting several work packages for the highway project near here.

Arthur called on the people to be patient while the implementation of the project is resumed, especially for the Sandakan-Telupid route where several roads were badly damaged.

He said the contractor has begun paving the road for the public's safety, but he did not deny that there would still be some inconveniences experienced by road users due to the construction of the Pan Borneo Highway.

"However, this inconvenience is only temporary during the construction work. At the same time, the implementation status is progressing quite well," he also said.

The 58-km Sandakan-Telupid Road is an alignment under work packages 28, 29 and 30 of the Pan Borneo Highway project, launched by Prime Minister Datuk Seri Ismail Sabri Yaakob last November. The project involves a construction cost of RM877 million.

The scope of the road construction involves upgrading the two-way road (single carriageway) to a dual carriageway (four lanes), together with the construction of three new bridges and a multi-level interchange.

The work package is expected to take three years and is scheduled for completion in October 2024.

Get the latest news @ www.EdgeProp.my

Subscribe to our Telegram channel for the latest stories and updates

Click here for more property stories

Latest publications

Follow Us

Follow our channels to receive property news updates 24/7 round the clock.

whatsapp
telegram
facebook
CLOSEclear

Malaysia's Most
Loved Property App

The only property app you need. More than 200,000 sale/rent listings and daily property news.

App StoreGoogle Play
Mobile logo