Mid Valley fire: Power supply fully restored, says TNB

Bernama
15 August, 2023
Updated:over 2 years ago
  • “TNB would like to thank the Fire and Rescue Department, and we apologise for the inconvenience caused to the affected users.”

KUALA LUMPUR (May 17): The power supply disruption caused by the fire at the main intake substation (PMU) at Mid Valley Megamall was fully restored at 12.30pm on Wednesday (May 17), said Tenaga Nasional Bhd (TNB).

TNB chief grid officer Ir Dev Anandan said TNB’s inspection found that the PMU was tripped at 10.27am, causing power cuts from 10.51 am.

“The swift action of TNB’s technical team was able to restore electricity supply in stages, as early as 10.55am. Electricity supply was restored to most affected areas within an hour and a half,” he said.

Dev said the supply disruption involved limited areas around Mid Valley and a part of Desa Pantai.

He added that the transportation system at KL Sentral, however, was not affected due to different power supply sources.

“TNB would like to thank the Fire and Rescue Department, and we apologise for the inconvenience caused to the affected users,” Dev said.

He said consumers can call TNB Careline at 15454, if they have any queries regarding power supply disruptions.

A fire had broken out at Mid Valley Megamall on Wednesday morning, and several videos showing a black plume of smoke from the building had gone viral on social media.

Never miss out

Sign up to get breaking news, unique insights, event invites and more from EdgeProp.

Latest publications

Never miss out

Sign up to get breaking news, unique insights, event invites and more from EdgeProp.

CLOSEclear

Malaysia's Most
Loved Property App

The only property app you need. More than 200,000 sale/rent listings and daily property news.

App StoreGoogle Play
Mobile logo