• Deputy Minister of Local Government Development Akmal Nasrullah Mohd Nasir said the nine projects, involving 6,406 units, were completed following the setting up of the sick and abandoned private housing project task force early this year.

MELAKA (Sept 22): Construction of nine out of 22 housing projects under Perbadanan PR1MA Malaysia (PR1MA) nationwide that were categorised as sick or problematic projects had been completed as of July 31.

Deputy Minister of Local Government Development Akmal Nasrullah Mohd Nasir (pictured) said the nine projects, involving 6,406 units, were completed following the setting up of the sick and abandoned private housing project task force early this year.

"We aim to complete the remaining PR1MA projects, involving 9,528 units, within two years or before the end of 2024," he told a press conference after a working visit to the PR1MA Melaka Tengah 2 Project here on Friday.

Regarding the three PR1MA projects in Melaka, Akmal Nasrullah said two of them, namely the Melaka Tengah Residence Project 2 and the Klebang Residence Project 2, are now 90% completed.

"Both housing projects are expected to be completed by the first quarter of 2024, while the Bukit Katil Residency Project is expected to be completed by the end of next year,” he added.

Meanwhile, he said PR1MA will pay in stages the liquidated ascertained damages (LAD) estimated at RM6 million to the 273 buyers of the Klebang 2 Residency Project.

The initial payment of part of the LAD to two buyers had been made, he said, adding that for the Bukit Katil Residency Project, a total of 10 buyers will receive the LAD amounting to about RM70,000.

Looking to buy a home? Sign up for EdgeProp START and get exclusive rewards and vouchers for ANY home purchase in Malaysia (primary or subsale)!

SHARE
RELATED POSTS
  1. MVV Industrial Park project in Negeri Sembilan poised to achieve RM2.8 bil GDV
  2. Gamuda records RM195 mil net profit in 1QFY2024
  3. Gamuda bags RM1.77 bil Singapore MRT project