SunCon unit signs agreement with MRCB George Kent for LRT3 package

KUALA LUMPUR (Aug 20): Sunway Construction Group Bhd’s (SunCon) unit, Sunway Construction Sdn Bhd (SCSB) has signed an agreement with MRCB George Kent (MRCBGK) for Package GS07-08 of the Light Rail Transit Line 3 (LRT3) project from Bandar Utama to Johan Setia by Prasarana Malaysia Bhd.

In a filing with Bursa Malaysia yesterday, SunCon said the agreement was signed yesterday following the appointment of MRCBGK as a turnkey contractor as a result of the change from a project delivery partnership to a turnkey contract pursuant to a contract between Prasarana and MRCBGK.

"Pursuant to the agreement, the scope of works in the Package GS07-08 contract has been revised and agreed with the salient amendments," it said.

The amendments entailed changes in the design and scope of the project, and with this, a new revised contract price of RM1.295 billion is agreed between SCSB and MRCBGK; and the revised completion date for the project will be Nov 30, 2023.

The project included the construction and completion of guideway, stations, park and rides, ancillary buildings, and other associated works.

EdgeProp Malaysia Virtual Property Expo 2020 (VPEX 2020) is happening now! Find out more exclusive projects and exciting deals here

Stay safe. Keep updated on the latest news at www.EdgeProp.my 

Click here for more property stories.

Looking for properties to buy or rent? With >150,000 exclusive listings, including undervalued properties, from vetted Pro Agents, you can now easily find the right property on Malaysia's leading property portal EdgeProp! You can also get free past transacted data and use our proprietary Edge Reference Price tool, to make an informed purchase.
SHARE
RELATED POSTS
  1. Selangor assemblyman disappointed with ‘unprofessional manner’ of CMCO announcement
  2. Parkson Elite 1 Utama closed due to Covid-19 positive case
  3. Prasarana aims daily ridership of 1.1 mln by end-2020