Setiawangsa-Pantai Expressway to fully open from 11.59pm Friday night, no toll charge until Dec 2
After the one-month period, cars will be charged the highway’s toll rate of RM3.
After the one-month period, cars will be charged the highway’s toll rate of RM3.
As of now, the Malaysian government has not initiated any discussions regarding the HSR with the Singapore government, even during the recent two-day Malaysia-Singapore Leaders' Retreat, according to Transport Minister Anthony Loke.
Transport Minister Anthony Loke stated that this includes the construction of five new stations, the acquisition of three sets of three-car trains to maintain service intervals, upgrading of the train depot, as well as other expenses involving independent checking engineers, project management and legal fees.
This collaboration paves the way for I-Bhd to launch its latest five-dimensional edutainment facility with the latest immersive technology in i-City by December.
Transport Minister Anthony Loke stated that according to the bilateral agreement between Malaysia and Singapore for the implementation of the RTS project, one of the agreed-upon conditions is the termination of the Tebrau Shuttle service six months after the RTS becomes operational.
"If necessary, this system will continue to be developed by enabling the use of other payment modes such as QR code in the next phase of implementation.
Bukit Bintang Member of Parliament Fong Kui Lun pointed out that the Penang LRT project, spanning 23 stations, is estimated to cost RM10 billion, while the five revived stations under LRT3 will cost RM4.
Hasbi also noted that the main contractor of ECRL, China Communications Construction Sdn Bhd, has appointed various local companies to support the construction of the project amounting to 2,785 companies comprising subcontractors, consultants, suppliers and service providers.
As of end 3Q2023, line-wide progress of the LRT3 construction stood at 86.