Final cost of Penang LRT yet to be determined, says Loke
"I want to stress that the RM13 billion figure has not been finalised.
"I want to stress that the RM13 billion figure has not been finalised.
“The government will consider allowing them [including industry players at KHTP] to apply for the new electricity tariff to be implemented simultaneously with the rest of Peninsular Malaysia in July — we are evaluating this due to its financial cost implications.
While some of the variation works were "acknowledged" and paid by Turnpike, Turnpike did not revise the contract price to reflect these variations, they said.
The RM456 million project has faced several delays, with the previous targeted operational date being Jan 31 this year.
Loke also announced that he will visit Bangkok, Thailand, in either March or April this year to further discuss strategic collaboration aimed at improving the rail network, particularly the Pan-Asian rail system, which connects China, Singapore, and all countries in mainland Southeast Asia.
Transport Minister Anthony Loke Siew Fook explained that the HSR is fundamentally different from other rail projects, such as Keretapi Tanah Melayu Bhd’s (KTMB) operations, which are fully funded, maintained, and constructed by the government.
The rail line project was earlier estimated to cost as much as RM100 billion as a government-funded project.
Liew Chin Tong said the Malaysian government will take a cautious, evaluative stance to better understand how these proposed restrictions might influence future developments and partnerships.
Gamuda is on track to reach the RM40 billion to RM45 billion target by the end of 2025, the research house noted.
Once the notice to proceed is issued, Gamuda will have six years to complete the contract.