ECRL reaches 88% progress with completion of C1B Segment
Construction of the C1B Segment began in September 2022, covering a technically significant stretch between the Genting Tunnel exit and the Gombak Integrated Terminal Station.
Construction of the C1B Segment began in September 2022, covering a technically significant stretch between the Genting Tunnel exit and the Gombak Integrated Terminal Station.
"The three key components of this project have shown positive progress, with the RTS Link Depot at 90% completion, the Bukit Chagar Station at 73% and the ICQ Complex at 76.
MAHB said it has received data and assurance from the contractors about the train, but "the information provided has not instilled sufficient confidence in the current reliability of the aerotrain system".
It was reported on Saturday (Nov 1) that JS Link and Lynas Malaysia will develop a super magnet facility in Pahang, a project described as bolstering Malaysia’s role and opening downstream prospects in the rare-earth sector.
YTL AI Cloud will deliver one of the world’s most advanced supercomputers in Malaysia, powered by Nvidia’s Blackwell architecture.
Transport Minister Anthony Loke: Some disruptions are caused by technical errors that shouldn't have happened.
The non-binding MOU outlines a partnership model intended to connect Asean and global capital markets with ready-to-develop industrial zones in Johor.
"Khazanah's investment is based on the government's mandate to develop Iskandar Malaysia as a special economic corridor and this effort has been extended to Desaru Coast in line with the broader development efforts in Johor.
An open tender for the second main civil works package (CMC2)—which covers the alignment from Macallum to Penang Sentral, including a bridge across the Penang Strait—will be launched soon.
Rapid Rail Sdn Bhd reported that a technical investigation found that a greater number of fibre optic cables had been cut and stolen, requiring extensive repairs to ensure stable and safe operations can be resumed.